+x multiply.build
Loading...
Step 6 of 7 - RIBA Stage 3

Spatial Coordination: From Concept to Planning

Develop detailed spatial arrangements, coordinate with engineers, and prepare comprehensive planning submissions. This stage transforms your concept into buildable, submittable proposals.

Coordination Tasks

4 key areas to complete

Detailed Drawings Development
Structural Coordination
Planning Submission Prep
Statutory Approvals

⏱️ Stage 3 typically takes 6-8 weeks to complete

Your Spatial Coordination Checklist

Four critical tasks to transform your concept into detailed, coordinated proposals ready for planning submission.

1

Develop Detailed Drawings

Create accurate, dimensioned drawings showing all spatial relationships

Action:

Work with your architect to produce detailed floor plans, elevations, and sections at 1:100 scale.

💡 Planning officers need to understand exactly what you're proposing - clarity prevents delays

2

Coordinate Structural Elements

Integrate structural engineering requirements into the design

Action:

Review structural calculations, beam sizes, and foundation requirements with your structural engineer.

💡 Structural changes at this stage are much cheaper than during construction

3

Prepare Planning Submission

Compile all required documents and drawings for planning application

Action:

Gather planning drawings, design & access statement, and all supporting documents.

💡 Complete applications process 30% faster than incomplete submissions

4

Secure Statutory Approvals

Obtain any required pre-application advice or consultation responses

Action:

Submit pre-application enquiry if complex. Coordinate with Thames Water, highways, etc.

💡 Pre-app advice costs £300-600 but prevents £8,000+ planning appeals

Key Coordination Priorities

Focus on these four critical areas to ensure your design works functionally, technically, and legally.

🏠

Room Relationships

How spaces connect and flow together

  • Circulation routes between existing and new spaces
  • Natural light distribution throughout
  • Privacy and acoustic separation
  • Views and outlook from each room
⚙️

Technical Coordination

Integration of structure, services, and building fabric

  • Structural beam locations and sizes
  • Heating, plumbing, and electrical routes
  • Window and door opening coordination
  • Insulation and ventilation strategy
📋

Planning Compliance

Ensuring design meets planning policy requirements

  • Daylight/sunlight impact assessments
  • Privacy and overlooking compliance
  • Materials and design quality standards
  • Sustainable design requirements
🔨

Construction Feasibility

Practical buildability and access considerations

  • Construction sequence and phasing
  • Material delivery and storage
  • Scaffold and access requirements
  • Temporary works and protection

Why Proper Coordination is Critical

Taking time to coordinate properly at this stage prevents expensive problems and delays later.

⚠️

Prevents Construction Problems

Proper coordination identifies clashes before they become expensive site issues.

Cost of poor coordination: Poor coordination causes 60% of construction delays and adds £5,000-£15,000 in costs.

📐

Maximizes Space Efficiency

Careful spatial planning gets the most usable space from your available area.

Cost of poor coordination: Good spatial design can add 15-20% more usable space without increasing footprint.

Improves Planning Success

Well-coordinated drawings show professionalism and reduce planning officer queries.

Cost of poor coordination: Complete, coordinated submissions have 40% fewer information requests.

🔮

Future-Proofs Your Investment

Proper coordination considers future adaptability and maintenance access.

Cost of poor coordination: Well-coordinated designs require 50% fewer modifications during construction.

The Coordination Investment

Spending an extra 2-3 weeks on thorough coordination at Stage 3 typically saves 6-12 weeks of delays and £8,000-£20,000 in construction problems. It's one of the best investments in your project.

Planning Submission Requirements

Complete checklist of everything you'll need for your London planning application.

Essential Drawings

Included in architect's fee
  • Location plan (1:1250 scale)
  • Site plan showing proposal (1:500 or 1:200)
  • Existing and proposed floor plans (1:100)
  • Existing and proposed elevations (1:100)
  • Existing and proposed sections (1:100)

Supporting Documents

£500-£2,000 depending on complexity
  • Design and Access Statement
  • Planning Statement (if required)
  • Heritage Statement (if conservation area/listed)
  • Daylight/Sunlight Assessment (if required)

Specialist Reports

£800-£3,000 for specialist reports
  • Structural calculations summary
  • Energy/Sustainability Statement
  • Tree Survey (if trees affected)
  • Transport Statement (if access changes)

Application Fees

Set by government/council
  • Householder application: £206
  • Full planning application: £462
  • Prior approval application: £96
  • Pre-application advice: £180-£600

Total Planning Costs

Expect to budget £2,000-£6,000 total for planning submission costs including drawings, reports, and fees. Complex sites or conservation areas may require additional specialist reports.

London Planning Timeline

Understanding the planning process timeline helps you plan the next stages of your project.

1

Pre-Application

4-6 weeks

Optional but recommended for complex proposals

Key Activities:

Pre-application advice meeting
Written officer feedback
Guidance on likely issues
Recommended design changes
2

Application Submission

1-2 weeks prep

Compile and submit all required documents

Key Activities:

Complete application form
All required drawings and documents
Payment of application fees
Validation by planning department
3

Statutory Consultation

8 weeks

Public consultation and officer assessment

Key Activities:

Neighbor notification period
Officer site visit
Consultation responses
Officer report preparation
4

Decision

1-2 weeks

Planning committee or delegated decision

Key Activities:

Planning decision notice
Conditions and informatives
Appeal rights information
Implementation timeline

Planning Timeline Reality

While the statutory period is 8 weeks, most applications take 10-14 weeks due to information requests, consultation responses, and officer workload. Plan accordingly and submit early if you have a project deadline.

Common London Coordination Challenges

Specific issues you'll encounter in London's dense urban environment and how to address them.

Daylight and Rights to Light

Dense urban environment creates complex daylight challenges

💰 Typical cost: Daylight assessment: £1,500-£3,500

Solutions:

  • BRE daylight/sunlight analysis may be required
  • Consider neighbor impact early in design
  • Use roof lights and light wells strategically
  • Document existing light levels as baseline

Party Wall Coordination

Shared walls require careful structural coordination

💰 Typical cost: Party wall procedures: £2,000-£5,000

Solutions:

  • Early party wall surveyor appointment
  • Coordinate structural design with PW requirements
  • Plan construction sequence around PW procedures
  • Budget for potential neighbor upgrades

Access and Construction Logistics

Limited access complicates construction coordination

💰 Typical cost: Crane hire: £800-£1,500 per day

Solutions:

  • Plan material deliveries and storage
  • Consider crane and scaffold requirements
  • Coordinate with neighbors for access
  • Design for hand-portable materials where needed

Services and Utilities Coordination

Complex existing services require careful integration

💰 Typical cost: Utility surveys: £500-£1,500

Solutions:

  • Full utility survey before detailed design
  • Early coordination with utility companies
  • Plan new service routes carefully
  • Consider impact on neighbor services

Ready for Stage 4?

With planning submitted or approved, it's time to develop technical drawings for building regulations and construction.

Next: Stage 4 - Technical Design